    Sl No Major Milestones Original Targets as per L1 Fresh Targets of
    M/s. BHEL
    1 Boiler Drum Lifting
    13.04.08
    02.10.08 (Done)
    2 Start of TG & Condenser Erection
    24.06.08
    17.01.09
    3 Boiler Hydro Test
    27.12.08
    24.04.09
    4 Turbine & Generator Box-up
    26.01.09
    30.06.09
    5 Turbine On Barring Gear
    20.04.09
    25.08.09
    6 Boiler Light Up
    29.05.09
    30.08.09
    7 Synchronization
    20.07.09
    30.11.09
    8 Coal Firing & Continuous Operation of Unit
    08.09.09
    29.12.09
    9 Trial Operation Completion
    09.09.09
    28.01.10