| Sl No | Major Milestones | Original Targets as per L1 | Fresh Targets of M/s. BHEL |
| 1 | Boiler Drum Lifting | 13.04.08 | 02.10.08 (Done) |
| 2 | Start of TG & Condenser Erection | 24.06.08 | 17.01.09 |
| 3 | Boiler Hydro Test | 27.12.08 | 24.04.09 |
| 4 | Turbine & Generator Box-up | 26.01.09 | 30.06.09 |
| 5 | Turbine On Barring Gear | 20.04.09 | 25.08.09 |
| 6 | Boiler Light Up | 29.05.09 | 30.08.09 |
| 7 | Synchronization | 20.07.09 | 30.11.09 |
| 8 | Coal Firing & Continuous Operation of Unit | 08.09.09 | 29.12.09 |
| 9 | Trial Operation Completion | 09.09.09 | 28.01.10 |
Search
Latest topics
STPS Extension Unit No.6 (1 x 250MW) Major Milestones Committed by M/s. BHEL

sukantasenroy- Posts: 7
Join date: 2008-08-30
» .FLV - .MOV - .MP4 Thumbnails for Win XP | Add any extension and see a thumbnail of it...
» Mx-key v3.5 revision 1.2, Public-Release - MAJOR UPDATE - The only BOX with TMA included
» Business logos play a major part in overall business branding
» How to make Quality Assurance and unit tests for a DW/BI project?
» Dutch Triton pre-unit
» Mx-key v3.5 revision 1.2, Public-Release - MAJOR UPDATE - The only BOX with TMA included
» Business logos play a major part in overall business branding
» How to make Quality Assurance and unit tests for a DW/BI project?
» Dutch Triton pre-unit

» Progress/Program of M/s. BHEL for Major Balance Activities.
» Unit No.5 : Status of Pending BOP work.
» Unit No.5 : Status of Pending BOP work.
» Updated Status of Balance work on Main Plant package
» Updated Status of Unit-5 Balance Work for BOP Package
» Status Report of Unit No.6 Construction as on 12.03.09.
» [b]Progress of Unit No.5 BOP Construction as on date 20.02.09.[/b]
» [b]Updated Progress of Unit No.6 Construction Work as on 20.02.09.[/b]