Santaldih Thermal Power Station - WBPDCL

This site is made for sharing information of STPS & on going projects at STPS - Unit#5 and Unit#6


    Updated Status of Balance work on Main Plant package

    Share

    mbdcl

    Posts : 9
    Join date : 2009-02-04

    Updated Status of Balance work on Main Plant package

    Post  mbdcl on 13th March 2009, 18:00

    Fixing Balance Door & Windows and all Rolling Shutters
    Sl No

    [/center]Description[/center]
    Cumulative Progress

    Virtually no progress in this month
    A

    Power House Building
    1

    Brickwork/Facia/plaster balance on A row EL 0.M to EL 13.5/8.5M

    Above 13.5M, major work completed. 0.0M to 8.5M is in slow progress for manpower crisis.
    2

    AHU rooms (pending work)
    AHU Rooms (on A-row) Finishing work in progress.
    AHU Room in B-C bay/ 19.5M no action.
    3

    DG Room

    4

    SWAS Room : False Ceiling & AC for Dry Room etc.

    5



    6

    7



    8



    9



    10