Santaldih Thermal Power Station - WBPDCL

This site is made for sharing information of STPS & on going projects at STPS - Unit#5 and Unit#6


    Progress/Program of M/s. BHEL for Major Balance Activities.

    Share

    mbdcl

    Posts : 9
    Join date : 2009-02-04

    Progress/Program of M/s. BHEL for Major Balance Activities.

    Post  mbdcl on 27th April 2009, 14:35

    Sl NoMajor Activities Progress Program
    1 Ash Handling Plant (Ash Disposal lines to Ash pond) Ash Disposal Lines – Completed partly. October’09
    2Ash Recovery system Ash Recovery Pump house-not started. Clarifier, Chemical house & Misc Sumps-Ordering incomplete/Drgs not available.Dec’09
    3Mill Reject system Mechanical & piping work in progress 31.05.09
    4 Fire Hydrant & Detection system Incomplete 15.05.09
    5 Illumination Main Plant incomplete & BOP areas-almost nil 31.05.09
    6Delivery of Fire Tender Ordered this month 31.10.09
    7 Boiler LiftCivil work incomplete 07.06.09
    8Lifts in Power House, Technical Bldg & Mill Bldg Civilwork incomplete 30.10.09


    Last edited by mbdcl on 28th April 2009, 19:39; edited 1 time in total (Reason for editing : Updating)