Sl No | [/center]Description[/center] | Cumulative Progress |
| Virtually no progress in this month A | Power House Building | |
1 | Brickwork/Facia/plaster balance on A row EL 0.M to EL 13.5/8.5M | Above 13.5M, major work completed. 0.0M to 8.5M is in slow progress for manpower crisis. |
2 | AHU rooms (pending work) | AHU Rooms (on A-row) Finishing work in progress. AHU Room in B-C bay/ 19.5M no action. |
3 | DG Room | |
4 | SWAS Room : False Ceiling & AC for Dry Room etc. | |
5 | | |
6 | ||
7 | | |
8 | | |
9 | | |
10 | ||
Search
Latest topics
Updated Status of Balance work on Main Plant package

mbdcl- Posts: 9
Join date: 2009-02-04


» Progress/Program of M/s. BHEL for Major Balance Activities.
» Unit No.5 : Status of Pending BOP work.
» Unit No.5 : Status of Pending BOP work.
» Updated Status of Balance work on Main Plant package
» Updated Status of Unit-5 Balance Work for BOP Package
» Status Report of Unit No.6 Construction as on 12.03.09.
» [b]Progress of Unit No.5 BOP Construction as on date 20.02.09.[/b]
» [b]Updated Progress of Unit No.6 Construction Work as on 20.02.09.[/b]