Santaldih Thermal Power Station - WBPDCL

This site is made for sharing information of STPS & on going projects at STPS - Unit#5 and Unit#6

Latest topics

  • Post new topic
  • Reply to topic

Progress/Program of M/s. BHEL for Major Balance Activities.

Share

mbdcl

Posts: 9
Join date: 2009-02-04

Progress/Program of M/s. BHEL for Major Balance Activities.

Post  mbdcl on 27th April 2009, 13:05

Sl NoMajor Activities Progress Program
1 Ash Handling Plant (Ash Disposal lines to Ash pond) Ash Disposal Lines – Completed partly. October’09
2Ash Recovery system Ash Recovery Pump house-not started. Clarifier, Chemical house & Misc Sumps-Ordering incomplete/Drgs not available.Dec’09
3Mill Reject system Mechanical & piping work in progress 31.05.09
4 Fire Hydrant & Detection system Incomplete 15.05.09
5 Illumination Main Plant incomplete & BOP areas-almost nil 31.05.09
6Delivery of Fire Tender Ordered this month 31.10.09
7 Boiler LiftCivil work incomplete 07.06.09
8Lifts in Power House, Technical Bldg & Mill Bldg Civilwork incomplete 30.10.09


Last edited by mbdcl on 28th April 2009, 18:09; edited 1 time in total (Reason for editing : Updating)
  • Post new topic
  • Reply to topic

Current date/time is 22nd March 2010, 04:46