BOILER
25th April’08 is zero date of 6th unit, STPS (1x250 MW). KPEL is the subcontractor, who is taking care the Boiler Erection.Total non pressure parts erection quantity is 1543.16 MT including alignment, bolting & welding support and pressure parts erection quantity is 205.71 MT so far.
Out of 30 columns so far 23 has been erected along with 5 girders. Boiler drum has been lifted on 2nd oct. 2008.
Boiler main column =13/13
Auxiliary column =10/11
Air pre-heater main column=0/6
Four I BR welder selected in presence of boiler inspector for pressure parts.
Pressure welding completed so far
Joints are as follows:
TOTAL NO.S of LTSH joint : 198/682
Down comer:
NO. OF JOINT: 6/56
Details:
DC-2J2; DC-5J2 ; DC-6J4 & DC-1J4
DC-4J2;
Header lifted:
TURBINE
Column erection is going on
ESP
Mechanical work is yet to start as civil foundation work is under progress.
Condensate storage tank (500 kl)
5th units as well as 6th unit CS tank are ready.


» Progress/Program of M/s. BHEL for Major Balance Activities.
» Unit No.5 : Status of Pending BOP work.
» Unit No.5 : Status of Pending BOP work.
» Updated Status of Balance work on Main Plant package
» Updated Status of Unit-5 Balance Work for BOP Package
» Status Report of Unit No.6 Construction as on 12.03.09.
» [b]Progress of Unit No.5 BOP Construction as on date 20.02.09.[/b]
» [b]Updated Progress of Unit No.6 Construction Work as on 20.02.09.[/b]